BORDEN, NEW PEKIN & CLARK COUNTY PROGRESS

The second section of Phase 1A of the trail scheduled to be completed is through Borden, New Pekin, and Clark County. In Borden, MAC Construction crews began work in late September 2024 to grade the trail. Additionally, asphalt on the trail began being laid down in October 2024. 

The Monon South Trail section through New Pekin and Clark County will be 10.6 miles in length. This stretch of the trail will be primarily made up of crushed aggregate material (7.4 miles) with paved sections (over 3 miles) through Borden and New Pekin. 

Once construction has started in these areas, project photos will be kept below.